Free checklist · First production run

First production run checklist: 30 checks before you pay the factory deposit

The first production run is where small gaps become expensive. A missing label, an unsigned golden sample or a vague payment term can cost a whole batch. Work through these 30 checks with your factory before you pay the deposit, and keep the evidence for each.

200+ products built12+ years in hardware30+ industries served

The 30 checks

Work through all 30 with your factory

Seven areas decide whether a first production run goes well. The PDF adds the evidence to ask your factory for on every check, with Owner, Date and Done columns to sign each one off.

0 of 30 done
A

The design is frozen

5 items

Download the sign-off sheet (PDF)

Every check with the evidence to ask your factory for, plus Owner, Date and Done columns to sign it off.

FAQ

Questions about a first production run

What should I check before paying a factory deposit?

That the design is frozen and signed off, the parts list has approved alternates, certification and labels are done, tooling is approved from real samples, and the order states payment terms, quality limits and inspection. The checklist covers 30 checks in seven areas.

What is a golden sample?

A signed-off unit that both you and the factory keep as the reference for every unit that follows. Without one, there is nothing to hold a batch against.

How do I protect myself in a first production order?

Agree in writing what counts as a defect, how units are inspected before shipping, and when each payment is due. The PDF adds the evidence to ask your factory for on every check, with Owner, Date and Done columns.

Is it really free?

Yes. Everything is on this page with no email needed. You only enter an email if you want the PDF copy.

Want an engineer to review your checklist before you pay?

Bring your checklist to a free 30-minute call. We’ll point out the gaps that usually cost first-time founders a batch.